Project Title | Client | Consultant | Contract Amount (R O) | Contract Duration |
---|---|---|---|---|
Construction of Afool Bridge at Dhofar Governorate, Sultanate of Oman | Ministry of Transport Directorate General of Roads and Land Transport (Governorate of Dhofar) | Al Manarah Engineering Consultancy LLC | OMR 3.1 million | 13.5 Months |
Start of the Project | Completion Date | Original Project Completion | Extension of Time if Granted | Scope of The Work |
---|---|---|---|---|
29th May 2022 | 08th July 2023 | On going | N/A | The scope of works of this project includes construction of a new Afool bridge which will overpass Wadi Afool around 18.00 meters over the existing wadi. For connecting the new bridge to the existing road, it is provided a rehabilitation/upgrade of approximately 1.00 km of existing road (before and after the new bridge location). The total length of the upgraded road will be around 1.300 meters, of which 300m for the new Afool bridge, and approximately 1,000 m for the approaching road. The upgraded road is single carriageway road (1 lane in each direction). |
Address:
Shanfari & Partners Co. LLC
PB No: 26, Postal Code 211
Salalah
Sultanate of Oman
Phone:
Fax:
Email:
info@spcoman.com